Prj Class |
Namespace: Aspose.Tasks
The Prj type exposes the following members.
Name | Description | |
---|---|---|
![]() ![]() ![]() | ActualsInSync |
Determines whether all actual works have been synchronized with the project.
|
![]() ![]() ![]() | AdminProject |
Determines whether a project is an administrative project.
|
![]() ![]() ![]() | AreEditableActualCosts |
Determines whether actual costs are editable.
|
![]() ![]() ![]() | Author |
The author of a project.
|
![]() ![]() ![]() | AutoAddNewResourcesAndTasks |
Determines whether new resources or tasks automatically added to a resource or task pool.
|
![]() ![]() ![]() | Autolink |
Determines whether inserted or moved tasks are auto linked.
|
![]() ![]() ![]() | BaselineForEarnedValue |
The specific baseline used to calculate Variance values.
|
![]() ![]() ![]() | Calendar |
The project calendar.
|
![]() ![]() ![]() | Category |
The category of a project.
|
![]() ![]() ![]() | Comments |
Project's comments.
|
![]() ![]() ![]() | Company |
The company where a project was created.
|
![]() ![]() ![]() | CreationDate |
The date and time when a project was created.
|
![]() ![]() ![]() | CriticalSlackLimit |
The number of days to the end of a task when Microsoft Project
marks that task as a critical task.
|
![]() ![]() ![]() | CurrencyCode |
The three letter currency character code as defined in ISO 4217.
Example of valid values is "USD".
|
![]() ![]() ![]() | CurrencyDigits |
The number of digits after a decimal symbol.
|
![]() ![]() ![]() | CurrencySymbol |
The currency symbol used in a project.
|
![]() ![]() ![]() | CurrencySymbolPosition |
The placement of the currency symbol.
|
![]() ![]() ![]() | CurrentDate |
The system date.
|
![]() ![]() ![]() | CustomDateFormat |
Project view custom date format. Used to format dates when DateFormat property is set to Custom.
|
![]() ![]() ![]() | DateFormat |
Project view date format.
|
![]() ![]() ![]() | DaysPerMonth |
The number of days per month.
|
![]() ![]() ![]() | DefaultFinishTime |
The default finish time of new tasks.
|
![]() ![]() ![]() | DefaultFixedCostAccrual |
The default type when fixed costs are accrued.
|
![]() ![]() ![]() | DefaultOvertimeRate |
The default overtime rate for new resources.
|
![]() ![]() ![]() | DefaultStandardRate |
The default standard rate for new resources.
|
![]() ![]() ![]() | DefaultStartTime |
The default start time of new tasks.
|
![]() ![]() ![]() | DefaultTaskEVMethod |
The default earned value method for tasks.
|
![]() ![]() ![]() | DefaultTaskType |
The default type of new tasks.
|
![]() ![]() ![]() | DurationFormat |
The format for expressing the bulk duration.
|
![]() ![]() ![]() | EarnedValueMethod |
The default method for calculating earned value.
|
![]() ![]() ![]() | ExtendedCreationDate |
Date used for calculation and reporting.
|
![]() ![]() ![]() | FinishDate |
The finish date of a project.
|
![]() ![]() ![]() | FiscalYearStart |
Determines whether the fiscal year numbering is used.
|
![]() ![]() ![]() | FyStartDate |
The month when fiscal year is starting.
|
![]() ![]() ![]() | Guid |
The GUID of the project.
|
![]() ![]() ![]() | HonorConstraints |
Determines whether tasks honor their constraint dates.
|
![]() ![]() ![]() | HyperlinkBase |
Project's hyperlink base.
|
![]() ![]() ![]() | InsertedProjectsLikeSummary |
Determines whether subtasks are calculated as summary tasks.
|
![]() ![]() ![]() | KeepTaskOnNearestWorkingTimeWhenMadeAutoScheduled |
Determines whether manual tasks must be kept on nearest working time when made as auto scheduled.
|
![]() ![]() ![]() | Keywords |
Project's keywords.
|
![]() ![]() ![]() | LastAuthor |
Project's last author.
|
![]() ![]() ![]() | LastPrinted |
Project's last print time.
![]() Saved in UTC format in mpp files.
DateTime type.
|
![]() ![]() ![]() | LastSaved |
The date when a project was saved last time.
![]() Saved in UTC format in mpp files.
DateTime type.
|
![]() ![]() ![]() | Manager |
The manager of a project.
|
![]() ![]() ![]() | MicrosoftProjectServerURL |
Determines whether a project was created by a Project Server user as opposed to an NT user.
|
![]() ![]() ![]() | MinutesPerDay |
The number of minutes per day.
|
![]() ![]() ![]() | MinutesPerWeek |
The number of minutes per week.
|
![]() ![]() ![]() | MoveCompletedEndsBack |
Determines whether the end of completed portions of tasks scheduled to start
after the status date but started earlier should be moved back to the status date.
|
![]() ![]() ![]() | MoveCompletedEndsForward |
Determines whether the end of completed portions of tasks scheduled
to have been completed before the status date but begun later
should be moved up to the status date.
|
![]() ![]() ![]() | MoveRemainingStartsBack |
Determines whether the beginning of remaining portions of tasks scheduled to start
after the status date but started earlier should be moved back to the status date.
|
![]() ![]() ![]() | MoveRemainingStartsForward |
Determines whether the beginning of remaining portions of tasks
scheduled to have begun later should be moved up to the status date.
|
![]() ![]() ![]() | MultipleCriticalPaths |
Determines whether multiple critical paths are calculated.
|
![]() ![]() ![]() | Name |
The name of the project.
|
![]() ![]() ![]() | NewTasksAreManual |
Determines whether new tasks created as manual.
|
![]() ![]() ![]() | NewTasksEffortDriven |
Determines whether new tasks are effort driven.
|
![]() ![]() ![]() | NewTasksEstimated |
Determines whether an estimated duration is shown by default.
|
![]() ![]() ![]() | NewTaskStartDate |
The default start date type for new tasks.
|
![]() ![]() ![]() | ProjectExternallyEdited |
Determines whether the project was externally edited.
|
![]() ![]() ![]() | RemoveFileProperties |
Determines whether all file properties will be removed on save.
|
![]() ![]() ![]() | Revision |
The number of times a project was saved.
|
![]() ![]() ![]() | SaveVersion |
The version of Microsoft Office Project from which a project file was saved.
|
![]() ![]() ![]() | ScheduleFromStart |
Determines whether to calculate the project schedule forward from the start date.
|
![]() ![]() ![]() | ShowProjectSummaryTask |
Determines whether to display summary information about an entire project on a single row with its own summary task bar at the top of the Gantt Chart view.
|
![]() ![]() ![]() | SplitsInProgressTasks |
Determines whether in-progress tasks can be split.
|
![]() ![]() ![]() | SpreadActualCost |
Determines whether actual costs are spread to the status date.
|
![]() ![]() ![]() | SpreadPercentComplete |
Determines whether a percent complete is spread to the status date.
|
![]() ![]() ![]() | StartDate |
The start date of a project.
|
![]() ![]() ![]() | StatusDate |
the status date to display progress or to calculate earned value totals.
The status date is the same as the current date (today's date) unless a different status date is specified.
|
![]() ![]() ![]() | Subject |
The subject of a project.
|
![]() ![]() ![]() | TaskUpdatesResource |
Determines whether updates to tasks update resources.
|
![]() ![]() ![]() | Template |
Project's template.
|
![]() ![]() ![]() | TimescaleFinish |
The date that the timescale in the view finishes.
|
![]() ![]() ![]() | TimescaleStart |
The date that the timescale in the view starts.
|
![]() ![]() ![]() | Title |
The title of a project.
|
![]() ![]() ![]() | Uid |
The unique Id of a project.
|
![]() ![]() ![]() | UpdateManuallyScheduledTasksWhenEditingLinks |
Determines whether manual tasks must be updated when links were edited.
|
![]() ![]() ![]() | WeekStartDay |
First day of a week.
|
![]() ![]() ![]() | WorkFormat |
The format used to show the duration of the task.
|
var project = new Project(DataDir + "Blank2010.mpp"); project.Set(Prj.Name, "Custom Project Name"); Console.WriteLine("Project name: " + project.Get(Prj.Name));